Monday, March 12, 2012

Schedule update

Spoke with our PM this morning and this is the plan:

Week of:
3/19 Lumber delivered-framing begins
3/26 Windows/doors delivered-installed same day as long as it's not raining
4/2 Brick arrives

PM suggests we set-up meeting with Guardian the first week of April to go over placement of the items we selected with them, speakers, data ports, etc.

Waterproofing should be finished up today and they'll start to fill in the dirt around the foundation tomorrow.  Next week will be a major week!  Can't wait.....

4 comments:

  1. Woohoo! Our waterproofing was done on Saturday, this are still on sched :) Ericka

    ReplyDelete
  2. Great news, we should all be finishing one after the other look forward to seeing your pictures.

    ReplyDelete
  3. Our backfilling was done yesterday, lumber will arrive Thursday and framing will be begin Friday. We have quite a group of bloggers that are all on about the same schedule!

    ReplyDelete
  4. Congrats to everyone! It's exciting to watch all of our journeys unfold. The framing process happens so fast, I can't wait to see everyone's pictures.

    ReplyDelete